Meeting Renovation
Printer-friendly version
Renovation News
- 2019 Updates
- September 8
- September 1
- August 25
- August 18
- August 11
- August 4
- July 28
- July 21
- July 14
- July 7
- June 30
- June 23
- June 16
- June 9
- June 2
- May 26
- May 19
- May 12
- May 5
- April 28
- April 21
- April 14
- April 7
- March 31
- March 24
- March 17
- March 10
- March 3
- February 24
- February 17
- February 10
- February 3
- January 27
- January 20
- January 13
- January 6
- 2018 Updates
- December 30
- December 23
- December 16
- December 9
- December 2
- November 25
- November 18
- November 11
- November 4
- October 28
- October 21
- October 14
- October 7
- September 30
- September 23
- September 16
- September 9
- September 2
- August 26
- August 19
- August 12
- August 5
- July 29
- July 22
- July 15
- July 8
- July 1
- June 24
- June 17 – Work Begins
- June 10
- June 3
- May 27
- May 20
- May 13
- May 6
- April 29
- April 22
- April 15
- April 8
- April 1
- March 25
- March 18
- March 11
- March 4
- February 25
- February 18
- February 11
- February 4
- October 2017 Update
- October 2016 Update
- July 2014 Video Update
- May 2013 Update
- June 2012 Concept Plans
- June 2011 Proposal
What is the renovation project?
The Friends Meeting of Washington has undertaken over 10 years of discernment, discussion, and planning for a major renovation of our space. Through this process, Friends have envisioned a renovation of our Meeting that meets three important goals:
- Accessibility: We'll install an elevator and passageways to connect the three buildings on our campus to each other (the Meetinghouse, Quaker House, and Carriage House).
- Environmental Stewardship: We'll make our gardens even more beautiful, functional, and accessible, while fixing long-standing drainage problems and reducing the amount of stormwater runoff from our property that enters DC's sewer system following a rain storm.
- Inclusivity and Welcoming: Through the above goals, we'll make our campus more inclusive of our members and attenders of all ages, including those with physical disabilities or mobility issues. We'll also provide a more welcoming space to visitors and other space users from the community.
How did we get here?
- 1930: Meetinghouse constructed. Totally inaccessible to those with physical limitations
- 1950: Meetinghouse expanded, including new Library, Decatur Place, and Terrace Rooms
- 1956: Ramp to Meeting Room north entrance added, making it accessible. Parlor and Library also accessible, via that entrance to the Meeting Room
- 1970: Meeting purchases Quaker House, Carriage House, and grounds
- 2002: Faith, Facilities, and Financial Realities (FFFR) process initiated to begin prayerful consideration of our renovation needs.
- 2003: FFFR Committee recommended that Meeting House be made accessible and our facilities used to greatest extent possible. Recommends Capital Campaign be organized.
- 2004: Threshing sessions, visits with Friends from other Meetings that had recently undertaken reonvations, and visits to these Meetings
- 2006: Quaker fundraising consultant engaged to help determine whether FMW could mount this renovation effort and raise the needed funds
- 2006: Meeting for Business approved the expenditure of funds on early design concepts
- 2008: Financing meetings with the School for Friends and other Quaker organizations to explore tenancy options
- 2010: Capital Campaign launched
- 2012: Meeting for Business approves current plan concept and we engage Quaker architect Evan Lippincott and archtecture and engineering firm Gauthier Alvarado Associates to move the design forward.
- 2013: Schematic Design set completed, showing addition and back garden design. Construction cost estimate $1.7 million
- 2014: Design Development set complete showing additional project details. Construction cost estimate $1.8 million
- 2015: Progress set civil engineering (stomwater and drainage) plans completed. Construction cost estimate grows to $2.7 million. Extended discussion of possible cost reduction changes.
- 2016: Bid set completed. Construction estimate grows to $2.9 million.
- 2017: Permit set completed and submitted to DC for permitting. Estimated construction contract grows to $3.8 million. Meeting approves borrowing up to $3.5 million. Mortgage negotiated with Sandy Spring Bank. Storm water management plan greatly revised.
- 2018: Contract negotiations with Monarc Construction begin the year, with rough contract cost estimate of $3.6 million. Construction set to begin in April and take about a year.
What will the renovation project look like and why is it needed?
The following 2014 videos provide an overview of the renovation project and how the FMW campus will benefit:
- FMW Renovation Plans (3 minutes)
- FMW Renovation Walkthrough (10 minutes)
- Full video including history of the buildings (27 minutes)
The project described in these plans is the current project, except that:
- We will not merge the remaining half of the Parlor with the Library, but will keep a smaller Parlor space and the present Library.
- We will add a new room in the current open deck space between Carriage House and Quaker House.
- There will be a 400-square-foot bioretention pond to capture stormwater at the lower end of the East Garden.
- We are enlarging the Assembly Room by replacing the wall between it and the Children's Library space with a folding wall, and we are upgrading the floor, ceiling, lighting and HVAC to make it a more spacious and attractive space.